Our Director – Adrian Bhreathnach takes us through a complex…

Background

The Sites

Site A

  • Glass Area 38,500 m2
  • Two Groundwater Abstractions
  • 80,000 litre Kerosene Fuel Storage

Site B

  • Glass Area 13,000 m2
  • One Groundwater Abstractions
  • >40,000 litre Kerosene Fuel Storage
  • Glass Area 13,000 m2

New Pit Chalk
East Anglia
Groundwater Source Protection Zone 2

The Release

Site B – Pump in Abstraction Well located at 25m bgl – Kerosene
Subsequently – Kerosene identified in Site A Abstraction Well (220m upgradient)

Loss of kerosene heating oil – 4No OST’s – >500 litres / hr usage @ <5oC

Source of kerosene identified as underground fuel oil delivery line over approximately 6 years

The Source

The Receptors